Oyebola Olugbemi - The Simplified Project Management Process
One of the challenges of explaining project management to people who are unfamiliar with the approach, is that descriptions are often either so high-level as to be meaningless, or so detailed that they are overwhelming. Over the years, I have come to use a model as a framework for introducing and discussing project management tools and techniques. It can be used as the basis for a five-minute explanation of what is involved in project management, but also as an outline for more detailed discussions. (The actual model can be found on the Key Consulting website under free templates and info.)
A brief description of each step follows:
Assemble Team
The project planning team will be assembled, including
appropriate representation from customers/clients, and sometimes subcontractors
and vendors. Initial roles and responsibilities will be defined.
Deliverables: Initial project setup documentation.
Define Project Objective
With the project team in place, the overall project purpose
will be verified and detailed project objectives developed. A phase-exit review
will be conducted to ensure that the project is ready to move into the next
phase, which is planning.
Deliverables: project charter, phase-exit review checklist.
Define Project Scope
An appropriately detailed Work Breakdown Structure (WBS)
will be developed to ensure the project scope is properly agreed to and
understood by all stakeholders. This also allows the complete project to be
split into appropriate sub-projects and/or phases.
Deliverables: Project work breakdown structure.
Construct an Initial Plan
Once tasks of an appropriate level have been identified in
the WBS, they will be organized by the project team into logical network
diagrams, with estimated durations. This allows the project manager to predict
when activities will be complete, assess the feasibility of target dates, and
identify the critical path for the project.
Deliverables: Initial work plan.
Add Resources, Costs, Risks, etc.
Certain project resources may be defined as critical
resources. In particular, the project manager may suspect that key project
staff may be faced with too much work. If so, estimated resource usage
information can be added to the project plan to allow resource forecasting.
Cost is obviously also critically important, and expenditures can be added to
the plan to create estimated cash-flow requirements. Risk management can also
be utilized on projects to provide a framework to better manage events that
occur beyond the control of the project team.
Deliverables: Resource availability and commitment profiles,
risk identification and control strategies, cash-flow forecasts.
Obtain Stakeholder Buy-in
To ensure the project is implemented as smoothly as
possible, with the support of the involved parties, it will be necessary to
review the initial plans with all the major project stakeholders and to solicit
buy-in from each one. A phase-exit review will be conducted to ensure that the
project is ready to move into the next phase, which is control.
Deliverables: Approved final plan, phase-exit review
checklist.
Publish the Plan
Once the plans are agreed to, they must be effectively
communicated to all stakeholders. This can be done in hard copy or via
electronic media, depending on the resources available. On most projects, a
communications plan will be developed, and distribution of the plans will
follow the guidelines laid out in the communications plan.
Deliverables: Plan published to all stakeholders.
Collect Progress Information
On a regular basis, the project manager will collect
progress information that has been reported by the project team. This will
allow the compilation of progress reports, such as:
Activities completed within the past two weeks
Activities forecast for the next two weeks with a focus on
activities on the critical path
Funds expended vs. fund expenditure forecast
Prioritized issues report
Metrics can also be developed to measure project progress in
other ways, such as earned value, or activity float statistics. If the project
manager reviews the progress data and concludes that the project is complete, a
phase-exit review will be completed to confirm that all the objectives have
been met before moving into the final closure phase.
Deliverables: Set of progress reports, set of exception
reports, metrics report, (phase-exit review checklist).
Analyze Current Status
By analyzing the progress information received, the project
manager will be able to augment the above reports with information about which
areas of the project are of concern and where problems are likely to occur in
the future. This allows managers to focus on the important/critical areas of
the project.
Deliverables: Project evaluation report(s).
Adjust the Plan, and Manage Project Change
Based on the analysis, and with the support of the project
team, the project manager will make plan adjustments to help reduce risks,
accommodate scope changes, or to compensate for activities that have not
occurred on schedule. Once this has happened, the plan will re-published and
the cycle repeated until the project is complete.
Deliverables: Change request forms, updated plan.
Close Project
When the objectives of the project have been achieved, the
project manager will close down the project. This will involve some financial
closure tasks, as well as archiving of the project materials. A lessons-learned
document will be developed to benefit future projects, and if possible a
project team celebration will be held.

Comments
Post a Comment